Foreword |
|
xi | |
Acknowledgments |
|
xv | |
Introduction to Third Edition |
|
xvii | |
|
|
1 | (12) |
|
|
1 | (1) |
|
The Primary Purpose of a Project Schedule |
|
|
2 | (3) |
|
Types of Project Schedules |
|
|
5 | (7) |
|
|
12 | (1) |
|
2 Float and the Critical Path |
|
|
13 | (22) |
|
|
13 | (6) |
|
|
19 | (3) |
|
|
22 | (1) |
|
What Is the Critical Path? |
|
|
23 | (1) |
|
Redefining the Critical Path as the Longest Path |
|
|
24 | (8) |
|
|
32 | (3) |
|
3 Reviewing the Project Schedule |
|
|
35 | (38) |
|
Reviewing the Baseline Schedule |
|
|
36 | (18) |
|
Approval Versus Acceptance |
|
|
54 | (1) |
|
Early Completion Schedules |
|
|
54 | (3) |
|
Reviewing a Schedule Update |
|
|
57 | (2) |
|
Steps to Review a Schedule Update |
|
|
59 | (14) |
|
4 Types of Construction Delays |
|
|
73 | (10) |
|
|
73 | (1) |
|
Critical Versus Noncritical Delays |
|
|
74 | (1) |
|
Excusable Versus Nonexcusable Delays |
|
|
75 | (2) |
|
Activity Delay Versus Project Delay |
|
|
77 | (2) |
|
No-Damage-For-Delay Clauses |
|
|
79 | (3) |
|
|
82 | (1) |
|
5 Measuring Delays---The Basics |
|
|
83 | (26) |
|
Delay Analysis Principles |
|
|
83 | (3) |
|
The Importance of Perspective |
|
|
86 | (5) |
|
Use the Contemporaneous Schedule to Measure Delay |
|
|
91 | (1) |
|
Do Not Create Schedules After the Fact to Measure Delays |
|
|
92 | (1) |
|
What to Do When There Is No Schedule? |
|
|
93 | (1) |
|
What Is As-Built Information? |
|
|
94 | (1) |
|
A Conceptual Approach to Analyzing Delays |
|
|
95 | (10) |
|
The Unique Position of Subcontractors |
|
|
105 | (4) |
|
6 Delay Analysis Using Bar Chart Schedules |
|
|
109 | (24) |
|
Defining the Critical Path |
|
|
110 | (1) |
|
Basic Critical Path Method |
|
|
111 | (2) |
|
Identifying the Critical Path on a Bar Chart |
|
|
113 | (5) |
|
Quantifying Delays Using Bar Chart Schedules |
|
|
118 | (6) |
|
Example Delay Analysis of Potential Changes With Bar Charts |
|
|
124 | (9) |
|
7 Delay Analysis Using Critical Path Method Schedules |
|
|
133 | (70) |
|
Using Critical Path Method Schedules to Measure Delays |
|
|
133 | (56) |
|
|
189 | (14) |
|
8 Delay Analysis Using No Schedules |
|
|
203 | (10) |
|
Use of Contemporaneous Documents for Sequence and Timing |
|
|
203 | (5) |
|
Using an As-Built Analysis to Quantify Delays |
|
|
208 | (5) |
|
9 Other Retrospective Delay Analysis Techniques---Their Strengths and Weaknesses |
|
|
213 | (38) |
|
Schedule-Based Delay Analysis Techniques |
|
|
214 | (1) |
|
As-Planned Versus As-Built Analysis |
|
|
214 | (2) |
|
Impacted As-Planned Analyses |
|
|
216 | (9) |
|
Collapsed As-Built Analyses |
|
|
225 | (3) |
|
Retrospective Time Impact Analysis |
|
|
228 | (15) |
|
|
243 | (1) |
|
But-For Schedules, Analyses, and Arguments |
|
|
244 | (3) |
|
Nonschedule-Based Analyses |
|
|
247 | (1) |
|
|
248 | (3) |
|
10 The Owner's Damages Due to Delay |
|
|
251 | (14) |
|
|
251 | (3) |
|
|
254 | (11) |
|
11 The Contractor's Damages Due to Delay |
|
|
265 | (24) |
|
|
265 | (1) |
|
|
266 | (2) |
|
|
268 | (2) |
|
|
270 | (1) |
|
|
270 | (1) |
|
|
271 | (3) |
|
|
274 | (1) |
|
General Guidelines for the Presentation and Recovery of Delay Costs |
|
|
274 | (3) |
|
Examples of Delay Cost Calculations |
|
|
277 | (12) |
|
|
289 | (16) |
|
What Is Home Office Overhead? |
|
|
289 | (2) |
|
Effects of Delays on Home Office Costs |
|
|
291 | (2) |
|
|
293 | (6) |
|
|
299 | (1) |
|
|
300 | (2) |
|
Calculation Using Actual Records |
|
|
302 | (1) |
|
|
303 | (2) |
|
13 Other Categories of Delay Costs |
|
|
305 | (8) |
|
Damages Associated With Noncritical Delays |
|
|
305 | (4) |
|
Consulting and Legal Costs |
|
|
309 | (1) |
|
Lost Profits/Opportunity Costs |
|
|
309 | (4) |
|
14 Inefficiency Caused by Delay |
|
|
313 | (8) |
|
|
313 | (1) |
|
Ways That Delay Can Lead to Inefficiencies |
|
|
313 | (5) |
|
|
318 | (1) |
|
Quantifying the Costs of Inefficiency |
|
|
319 | (2) |
|
|
321 | (14) |
|
|
321 | (2) |
|
Why Is a Project Accelerated? |
|
|
323 | (1) |
|
Constructive Acceleration |
|
|
323 | (1) |
|
How Is a Project Accelerated? |
|
|
324 | (2) |
|
Critical Path Shifts Due to Acceleration |
|
|
326 | (1) |
|
Quantifying the Time Savings Associated With Acceleration |
|
|
327 | (1) |
|
Quantifying the Costs of Acceleration |
|
|
328 | (7) |
|
16 Determining Responsibility for Delay |
|
|
335 | (6) |
|
|
335 | (2) |
|
Evaluating Responsibility |
|
|
337 | (1) |
|
|
338 | (3) |
|
17 Delay---Risk Management |
|
|
341 | (14) |
|
|
341 | (5) |
|
Construction Manager's Considerations |
|
|
346 | (2) |
|
General Contractor's Considerations |
|
|
348 | (2) |
|
Subcontractor's and Supplier's Considerations |
|
|
350 | (2) |
|
Design Consultant's Considerations |
|
|
352 | (1) |
|
Real-Time Claims Management |
|
|
353 | (2) |
|
18 Delays and the Contract |
|
|
355 | (32) |
|
Project Schedule Provisions |
|
|
355 | (22) |
|
Time Extension Provisions |
|
|
377 | (6) |
|
|
383 | (4) |
Index |
|
387 | |