Atjaunināt sīkdatņu piekrišanu

E-grāmata: International Construction Contracts: A Handbook [Wiley Online]

(Barrister at 3 Hare Court)
  • Formāts: 224 pages
  • Izdošanas datums: 25-Jan-2013
  • Izdevniecība: Wiley-Blackwell
  • ISBN-10: 1118498593
  • ISBN-13: 9781118498590
  • Wiley Online
  • Cena: 97,78 €*
  • * this price gives unlimited concurrent access for unlimited time
  • Formāts: 224 pages
  • Izdošanas datums: 25-Jan-2013
  • Izdevniecība: Wiley-Blackwell
  • ISBN-10: 1118498593
  • ISBN-13: 9781118498590
Many large construction projects, such as those in the Middle East or Asia Pacific, are international in scope with a range of contractors and subcontractors signing contracts for delivery of specified work or services. The contractual situation in these instances may be complex and potentially includes a range of standard and bespoke contractual arrangements. In addition, the parties to these contracts may be based in different parts of the world, and are often working to different legal systems and understandings. This can lead to confusion in the understanding, interpretation and execution of a given contract. International Construction Contracts provides concise and practical guidance to those involved in the negotiation and management of international construction and engineering contracts. It sets out in clear, straightforward language the main features of construction contracts and international dispute resolution procedures. It ensures the reader is aware of the issues that might arise on the contractual side of their project so that they may better protect their party's interests. Many of the features and points discussed are illustrated by reference to the popular FIDIC contracts and the book includes a commentary on the two most widely used FIDIC design-build forms, the Yellow and Silver Books. Also included in the book is a fully worked example of a typical ICC arbitration from start to finish, with "pleadings", a detailed case narrative and commentary on events, and an example arbitration award. The ICC and SIAC arbitration rules are also provided.

Written for construction professionals, the book will be of great interest to engineers, architects, project managers, quantity surveyors, contract managers and contract administrators working on international projects.
Preface xiii
Foreword xv
Vivian Ramsey
Acknowledgements xvii
About the Author xix
Part I
1(30)
1 Contract
3(12)
1.1 What is a contract?
3(1)
1.2 Agreement
4(1)
1.3 Do contracts need to be in writing?
5(1)
1.4 Other elements of a contract
5(1)
1.5 Capacity and authority
6(2)
1.6 Importance of a written contract
8(2)
1.6.1 Clarity and certainty
8(1)
1.6.2 Procedures
9(1)
1.6.3 Risk allocation
9(1)
1.7 What should a properly written construction contract cover?
10(4)
1.7.1 FIDIC contracts
11(1)
1.7.2 Programme
12(1)
1.7.3 Delays and extensions of time
12(1)
1.7.4 Delay damages
13(1)
1.8 Tailoring the contract
14(1)
2 Risk
15(12)
2.1 How risk may be allocated
15(1)
2.2 The `traditional' approach to risk
16(2)
2.3 EPC/turnkey projects
18(1)
2.4 BOT-type projects
18(4)
2.4.1 Parties to a BOT-type project
18(2)
2.4.2 Contracts involved in a BOT-type project
20(2)
2.5 The FIDIC Silver Book
22(2)
2.6 Particular risks: The unforeseen and design
24(3)
2.6.1 Unforeseeable physical conditions
24(1)
2.6.2 Design responsibility
24(3)
3 Types of Construction Contract
27(4)
3.1 Lump sum contracts
27(1)
3.2 Prime cost or reimbursable contracts
28(1)
3.3 Unit price contracts
28(1)
3.4 Target contracts
29(1)
3.5 Which contract?
29(2)
Part II
31(46)
4 The FIDIC Design-Build Contracts
33(44)
4.1 Some key general provisions
34(3)
4.1.1 Communications: Clause 1.3
34(1)
4.1.2 The law and the language of the contract: Clause 1.4
35(1)
4.1.3 The priority of documents: Clause 1.5
35(1)
4.1.4 Compliance with laws: Clause 1.13
36(1)
4.2 The Employer
37(2)
4.2.1 The right of access to, and possession of, the site: Clause 2.1
37(1)
4.2.2 Evidence of the Employer's financial arrangements: Clause 2.4
37(1)
4.2.3 Employer's claims against the Contractor: Clause 2.5
38(1)
4.3 Contract administration: Clause 3
39(2)
4.3.1 The role of the Engineer
39(1)
4.3.2 `Determinations' in the Yellow and Silver Books
40(1)
4.3.3 Employer's Representative in the Silver Book
41(1)
4.3.4 The giving of instructions
41(1)
4.4 The Contractor
41(5)
4.4.1 The Contractor's general obligation: Clause 4.1
41(2)
4.4.2 `The works' which must fit the intended purpose: Clause 4.1
43(1)
4.4.3 Securing performance: Clause 4.2
43(1)
4.4.4 Contractor's Representative: Clause 4.3
44(1)
4.4.5 Subcontracting: Clauses 4.4 and 4.5
44(1)
4.4.6 Setting out: Clause 4.7
44(1)
4.4.7 Sufficiency of the Contract Price (Silver Book) or Accepted Contract Amount (Yellow Book): Clause 4.11
45(1)
4.4.8 Unforeseeable difficulties/physical conditions: Clause 4.12
45(1)
4.4.9 Progress reports: Clause 4.21
45(1)
4.5 Design
46(1)
4.5.1 The Contractor's general design obligations (Yellow and Silver Books): Clause 5.1
46(1)
4.5.2 Contractor's documents: Clause 5.2
46(1)
4.5.3 Contractor's undertaking: Clause 5.3
47(1)
4.6 Staff and labour: Clause 6
47(1)
4.7 Plant, materials and workmanship
48(2)
4.7.1 Executing the works: Clause 7.1
48(1)
4.7.2 Samples: Clause 7.2
48(1)
4.7.3 Inspections: Clause 7.3
48(1)
4.7.4 Testing: Clause 7.4
49(1)
4.7.5 Rejection and remedial work: Clauses 7.5 and 7.6
49(1)
4.7.6 Ownership: Clause 7.7
50(1)
4.8 Time: commencement, delays and suspension of the works
50(3)
4.8.1 Commencement and time for completion of the works: Clauses 8.1 and 8.2
50(1)
4.8.2 Programme: Clause 8.3
50(2)
4.8.3 Delays and extensions of time: Clause 8.4
52(1)
4.8.4 Suspension of the works: Clauses 8.8 to 8.10
52(1)
4.8.5 Prolonged suspension: Clause 8.11
53(1)
4.9 Tests on completion
53(1)
4.9.1 Contractor's obligations: Clause 9.1
53(1)
4.9.2 Delayed tests: Clause 9.2
54(1)
4.9.3 Re-testing: Clauses 9.3 and 9.4
54(1)
4.10 Employer's taking over
54(2)
4.10.1 Taking over of the works: Clause 10.1
54(1)
4.10.2 Taking over of part of the works: Clause 10.2
55(1)
4.11 Defects liability
56(2)
4.11.1 The Defects Notification Period: Clauses 11.1 to 11.3
56(1)
4.11.2 Failure to remedy defects: Clause 11.4
56(1)
4.11.3 Extending the DNP: Clause 11.3
57(1)
4.11.4 Further tests: Clause 11.6
57(1)
4.11.5 The Performance Certificate: Clause 11.9
57(1)
4.11.6 Unfulfilled obligations: Clause 11.10
58(1)
4.12 Tests after completion
58(1)
4.13 Variations and adjustments to the contract price
58(2)
4.13.1 Right to vary: Clause 13.1
58(1)
4.13.2 Variation procedure and value engineering: Clauses 13.2 and 13.3
59(1)
4.13.3 Changes in legislation: Clause 13.7
59(1)
4.13.4 Cost fluctuations: Clause 13.8
60(1)
4.14 Payment
60(4)
4.14.1 Interim payments: Clause 14.3
60(1)
4.14.2 Timing of interim payments: Clause 14.7
61(1)
4.14.3 Advance payment: Clause 14.2
61(1)
4.14.4 Retention money: Clauses 14.3 and 14.9
61(1)
4.14.5 Delayed payment and the right to financing charges: Clause 14.8
62(1)
4.14.6 Financial steps after Taking Over: Clauses 14.10 to 14.13
63(1)
4.14.7 Cessation of Employer's liability: Clause 14.14
64(1)
4.15 Termination by the Employer
64(2)
4.15.1 Termination for Contractor default: Clause 15.2
65(1)
4.15.2 Valuation for works executed at date of termination: Clause 15.3
66(1)
4.15.3 Payments after termination: Clause 15.4
66(1)
4.15.4 Termination for convenience: Clause 15.5
66(1)
4.16 Suspension and termination by the Contractor
66(2)
4.16.1 Suspension: Clause 16.1
66(1)
4.16.2 Termination: Clause 16.2
67(1)
4.16.3 Events after termination: Clause 16.3
67(1)
4.16.4 Payment on termination: Clause 16.4
67(1)
4.17 Risk and responsibility
68(3)
4.17.1 Indemnities: Clause 17.1
68(1)
4.17.2 Contractor's care of the works: Clause 17.2
69(1)
4.17.3 Specific Employer's risks: Clauses 17.3 and 17.4
69(1)
4.17.4 Limitation of liability: Clause 17.6
70(1)
4.18 Insurance
71(1)
4.19 Force majeure
71(3)
4.19.1 Meaning of `force majeure': Clause 19.1
71(1)
4.19.2 Notice: Clause 19.2
72(1)
4.19.3 Minimising delay and the consequences of force majeure: Clauses 19.3 and 19.4
72(1)
4.19.4 Prolonged force majeure: Clause 19.6
73(1)
4.19.5 Release from performance under the law: Clause 19.7
73(1)
4.20 Contractor's claims, disputes and arbitration
74(3)
4.20.1 Contractor's claims: Clause 20.1
74(3)
Part III
77(28)
5 Disputes and How to Resolve Them
79(26)
5.1 Introduction
79(1)
5.2 Legal aspects of a construction project
79(3)
5.2.1 The terms of the construction contract
80(1)
5.2.2 The law which governs the construction contract
80(1)
5.2.3 The terms of the construction contract relating to the resolution of disputes between the parties
80(1)
5.2.4 The law of the process for resolving a dispute
81(1)
5.2.5 Rights and liabilities that might arise independently of any contract
81(1)
5.2.6 The law which applies to a project by virtue of its location
82(1)
5.3 Kinds of claim
82(2)
5.3.1 Claims for which the contract specifically provides
82(1)
5.3.2 Claims for which the contract does not specifically provide
83(1)
5.4 Making a claim
84(2)
5.4.1 Do I have a claim?
84(1)
5.4.2 If I have a claim, when do I make it?
85(1)
5.4.3 How do I make my claim?
85(1)
5.4.4 Summary
86(1)
5.5 Who decides whether to accept a claim?
86(1)
5.6 The FIDIC Dispute Adjudication Board
87(3)
5.6.1 Scope
88(1)
5.6.2 Appointment of the DAB
88(1)
5.6.3 Referring a dispute
89(1)
5.6.4 Reaching a decision
89(1)
5.6.5 Informal opinion?
89(1)
5.6.6 Arbitration?
90(1)
5.7 Methods of dispute resolution
90(4)
5.7.1 Final methods of dispute resolution
90(2)
5.7.2 Informal methods of dispute resolution
92(1)
5.7.3 Arbitration or litigation?
93(1)
5.8 Arbitration
94(5)
5.8.1 The arbitration agreement
95(1)
5.8.2 The place of arbitration
95(1)
5.8.3 Arbitration institutions
95(1)
5.8.4 Commencement of an arbitration
96(1)
5.8.5 Conduct of the arbitration
96(1)
5.8.6 The arbitration award and challenges to the award
97(1)
5.8.7 Enforcement of arbitral awards
98(1)
5.9 How are international arbitrations conducted?
99(6)
5.9.1 The traditional arbitration centres
99(2)
5.9.2 ICC arbitration
101(4)
Appendix I Yugo Design Company v Sino Industries Corporation: An International Chamber of Commerce Arbitration 105(32)
Appendix IIA Rules of Arbitration of the International Chamber of Commerce 137(40)
Appendix IIB Rules of Arbitration of the Singapore International Arbitration Centre 177(20)
Index 197
William Godwin is a barrister specialising in construction, engineering, energy and infrastructure projects and has over twenty years experience of international construction acting for contractors, employers, developers and consultants in projects of all kinds. A regular speaker at the FIDIC international users conferences, William conducts accredited training in the FIDIC contracts through Matrix Seminars, is an arbitration panel member of the China International Economic and Trade Arbitration Commission and the Dubai International Arbitration Centre, and an approved adjudicator of the English Technology and Construction Bar Association.