Preface |
|
xxv | |
List of Figures |
|
xxix | |
List of Tables |
|
xxxi | |
List of Boxes |
|
xxxiii | |
Acknowledgments |
|
xxxvii | |
Part I Introduction |
|
1 | (152) |
|
Chapter 1 Introduction to PPP and Finance |
|
|
3 | (14) |
|
|
4 | (8) |
|
|
4 | (5) |
|
1.1.2 Common Labels for PPP Transactions |
|
|
9 | (1) |
|
|
10 | (2) |
|
1.2 PPP Can Be Costly and Slow, Why Bother? |
|
|
12 | (2) |
|
|
14 | (3) |
|
Chapter 2 Introduction to Project Finance |
|
|
17 | (36) |
|
|
18 | (1) |
|
2.2 Limited Recourse and Sponsor Support |
|
|
18 | (2) |
|
|
20 | (2) |
|
|
22 | (4) |
|
2.4.1 Debt-Equity (D/E) Ratio |
|
|
23 | (1) |
|
2.4.2 Loan Life Cover Ratio |
|
|
23 | (1) |
|
2.4.3 Debt Service Cover Ratio |
|
|
23 | (1) |
|
|
24 | (2) |
|
2.5 Certainty of Revenue Stream |
|
|
26 | (1) |
|
2.6 Public Sector Support |
|
|
26 | (2) |
|
|
28 | (7) |
|
2.7.1 The Construction Stage |
|
|
29 | (1) |
|
2.7.2 The Operation Stage |
|
|
30 | (3) |
|
|
33 | (1) |
|
2.7.4 Repayment and Pre-payment |
|
|
34 | (1) |
|
|
34 | (1) |
|
|
35 | (1) |
|
|
35 | (13) |
|
2.8.1 Equity Contributions |
|
|
35 | (1) |
|
|
36 | (3) |
|
2.8.2.1 The Relative Benefits of Different Lenders |
|
|
36 | (1) |
|
|
37 | (1) |
|
2.8.2.3 Shari'a Financing |
|
|
37 | (1) |
|
|
38 | (1) |
|
|
38 | (1) |
|
2.8.3 Mezzanine/Subordinated Contributions |
|
|
39 | (2) |
|
2.8.3.1 Nature of Subordination |
|
|
39 | (1) |
|
2.8.3.2 Mezzanine Financiers |
|
|
40 | (1) |
|
2.8.3.3 Form of Mezzanine Finance |
|
|
40 | (1) |
|
2.8.3.4 Reasons for Mezzanine Finance |
|
|
40 | (1) |
|
2.8.4 Conditions Precedent |
|
|
41 | (1) |
|
2.8.4.1 Commercial and Legal Arrangements |
|
|
41 | (1) |
|
2.8.4.2 Financial Ratios and Covenants |
|
|
42 | (1) |
|
|
42 | (1) |
|
2.8.5 Hedging and Futures Contracts |
|
|
42 | (1) |
|
2.8.6 Shareholder Support |
|
|
43 | (1) |
|
|
43 | (2) |
|
|
44 | (1) |
|
|
44 | (1) |
|
|
44 | (1) |
|
2.8.8 Warranties, Undertakings and Representations |
|
|
45 | (1) |
|
|
46 | (1) |
|
2.8.10 Inter-creditor Issues and Security Trustee |
|
|
46 | (1) |
|
2.8.11 Lenders' Technical Adviser |
|
|
47 | (1) |
|
2.8.12 Termination Compensation |
|
|
47 | (1) |
|
2.9 Other Risk Issues Relevant to Financing |
|
|
48 | (5) |
|
|
48 | (1) |
|
2.9.2 Force Majeure and Change in Law |
|
|
49 | (1) |
|
|
49 | (1) |
|
|
49 | (1) |
|
2.9.5 Currency Exchange Risk |
|
|
50 | (1) |
|
|
50 | (1) |
|
|
51 | (2) |
|
Chapter 3 Introduction to PPP through BOT Projects |
|
|
53 | (24) |
|
|
54 | (3) |
|
3.2 BOT Project Agreements |
|
|
57 | (5) |
|
3.2.1 Financing Agreement |
|
|
58 | (1) |
|
3.2.2 Shareholders' Agreement |
|
|
59 | (1) |
|
3.2.3 Concession Agreement |
|
|
59 | (1) |
|
3.2.4 Offtake Purchase Agreement |
|
|
59 | (1) |
|
3.2.5 Input Supply Agreement |
|
|
60 | (1) |
|
3.2.6 Construction Contract |
|
|
60 | (1) |
|
3.2.7 Operation and Maintenance Agreement |
|
|
61 | (1) |
|
|
61 | (1) |
|
3.3 Parties Involved in a BOT Project |
|
|
62 | (10) |
|
|
62 | (1) |
|
3.3.2 Contracting Agency and Host Government |
|
|
62 | (4) |
|
3.3.2.1 Host Government Interests |
|
|
63 | (1) |
|
3.3.2.2 Host Government Involvement |
|
|
64 | (1) |
|
3.3.2.2.1 Invitation to Tender |
|
|
64 | (1) |
|
|
64 | (1) |
|
3.3.2.2.3 Attracting Investment |
|
|
64 | (1) |
|
3.3.2.2.4 Political Marketing |
|
|
65 | (1) |
|
3.3.2.2.5 Setting of Government Policy |
|
|
65 | (1) |
|
3.3.2.2.6 Provision of Information Basic to the Feasibility of the Project |
|
|
65 | (1) |
|
|
65 | (1) |
|
3.3.2.2.8 Assistance with Finance |
|
|
65 | (1) |
|
|
65 | (1) |
|
3.3.3 Multilateral, Bilateral and Export Credit Agencies |
|
|
66 | (2) |
|
3.3.3.1 Multilateral Agencies and Bilateral Agencies |
|
|
66 | (1) |
|
3.3.3.2 Export Credit Agencies |
|
|
67 | (1) |
|
|
68 | (1) |
|
3.3.5 Construction Contractor |
|
|
69 | (1) |
|
|
70 | (1) |
|
|
71 | (1) |
|
|
72 | (1) |
|
|
72 | (1) |
|
3.4 Stages of Development and Negotiation of a BOT Project |
|
|
72 | (5) |
|
|
77 | (28) |
|
|
78 | (8) |
|
4.1.1 Economic/Political Viability |
|
|
79 | (2) |
|
|
81 | (1) |
|
|
81 | (1) |
|
4.1.2.2 Availability of Justice |
|
|
81 | (1) |
|
|
81 | (1) |
|
|
81 | (1) |
|
|
82 | (1) |
|
4.1.2.6 Stability of the Tax Regime |
|
|
82 | (1) |
|
4.1.3 Financial Viability |
|
|
82 | (3) |
|
4.1.3.1 Debt-to-Equity Ratio |
|
|
83 | (1) |
|
4.1.3.2 Debt Service Cover Ratio |
|
|
84 | (1) |
|
4.1.3.3 Loan Life Cover Ratio |
|
|
84 | (1) |
|
|
85 | (1) |
|
4.1.4 Technical Viability |
|
|
85 | (1) |
|
|
86 | (7) |
|
|
87 | (2) |
|
4.2.1.1 Host Country Guarantees |
|
|
87 | (1) |
|
4.2.1.2 Host Country Policy |
|
|
87 | (1) |
|
4.2.1.3 Change in Political Atmosphere |
|
|
87 | (1) |
|
4.2.1.4 Nationalisation and Expropriation |
|
|
88 | (1) |
|
|
88 | (1) |
|
4.2.2 Administrative Issues |
|
|
89 | (2) |
|
4.2.2.1 Licences, Permits and Authorisations |
|
|
89 | (1) |
|
|
90 | (1) |
|
4.2.2.3 Administrative Policy |
|
|
91 | (1) |
|
|
91 | (1) |
|
|
91 | (2) |
|
4.2.4.1 Local Market for Offtake |
|
|
91 | (1) |
|
4.2.4.2 Local Market for Input |
|
|
92 | (1) |
|
4.2.4.3 Infrastructure Issues |
|
|
92 | (1) |
|
|
92 | (1) |
|
|
93 | (1) |
|
4.3 Source Country Issues |
|
|
93 | (1) |
|
4.4 Project Structure Issues |
|
|
93 | (3) |
|
|
94 | (1) |
|
4.4.2 Financing Structure |
|
|
94 | (1) |
|
4.4.3 Third-Party Risk Allocation |
|
|
95 | (1) |
|
|
95 | (1) |
|
4.4.3.2 Environmental and Other Legal/Regulatory Issues |
|
|
96 | (1) |
|
|
96 | (9) |
|
4.5.1 Concession Agreement |
|
|
96 | (3) |
|
|
97 | (1) |
|
|
97 | (1) |
|
|
97 | (1) |
|
4.5.1.4 Contracting Agency |
|
|
98 | (1) |
|
|
98 | (1) |
|
4.5.1.6 Change in Law/Regulations |
|
|
98 | (1) |
|
4.5.1.7 Licences and Permits |
|
|
98 | (1) |
|
4.5.1.8 Assignment and Security |
|
|
98 | (1) |
|
4.5.2 Construction Contract |
|
|
99 | (1) |
|
|
99 | (1) |
|
|
99 | (1) |
|
4.5.2.3 Liability Limitations |
|
|
99 | (1) |
|
|
100 | (1) |
|
|
100 | (1) |
|
|
100 | (1) |
|
|
100 | (1) |
|
4.5.3 Operation and Maintenance Agreement |
|
|
100 | (2) |
|
|
101 | (1) |
|
|
101 | (1) |
|
4.5.3.3 Replacement of Operator |
|
|
101 | (1) |
|
4.5.3.4 Major Maintenance |
|
|
102 | (1) |
|
4.5.4 Offtake Purchase Agreement |
|
|
102 | (1) |
|
|
102 | (1) |
|
|
102 | (1) |
|
|
103 | (1) |
|
4.5.5 Input Supply Agreement |
|
|
103 | (4) |
|
4.5.5.1 Failure to Deliver |
|
|
103 | (1) |
|
|
104 | (1) |
|
|
104 | (1) |
|
4.5.5.4 Supplier Infrastructure |
|
|
104 | (1) |
|
|
104 | (1) |
|
Chapter 5 Allocation of Risk |
|
|
105 | (36) |
|
5.1 Assessment and Allocation of Risk |
|
|
107 | (6) |
|
|
107 | (2) |
|
|
109 | (4) |
|
|
113 | (1) |
|
|
114 | (3) |
|
|
114 | (2) |
|
|
116 | (1) |
|
5.3.3 Time for Completion |
|
|
116 | (1) |
|
|
117 | (6) |
|
|
117 | (1) |
|
5.4.2 Interest Rate and Refinancing Risk |
|
|
118 | (1) |
|
|
119 | (1) |
|
|
119 | (1) |
|
5.4.5 Input Price Increase |
|
|
120 | (1) |
|
5.4.6 Construction Cost Increase |
|
|
120 | (1) |
|
5.4.7 Operation Cost Increase |
|
|
121 | (1) |
|
5.4.8 Cost of Spare and Replacement Parts |
|
|
121 | (1) |
|
5.4.9 Decrease in Offtake Price |
|
|
122 | (1) |
|
5.4.10 Coverage of Cost Overrun Risk |
|
|
122 | (1) |
|
|
122 | (1) |
|
|
122 | (1) |
|
5.4.10.3 Standby Credit Facility |
|
|
123 | (1) |
|
5.4.10.4 Risks Arising between Bid Submission and Financial Close |
|
|
123 | (1) |
|
|
123 | (2) |
|
5.5.1 Design and Construction |
|
|
123 | (1) |
|
|
124 | (1) |
|
|
124 | (1) |
|
5.5.4 Offtake Infrastructure |
|
|
124 | (1) |
|
|
125 | (2) |
|
5.6.1 Operating Standards |
|
|
126 | (1) |
|
5.6.2 Transfer of Know-How and Training |
|
|
126 | (1) |
|
|
126 | (1) |
|
|
127 | (1) |
|
5.7.1 Offtake (Output) Price |
|
|
127 | (1) |
|
|
127 | (1) |
|
|
128 | (7) |
|
5.8.1 Authority and Enabling Legislation |
|
|
128 | (1) |
|
5.8.2 Change in Budget, Government or Political Atmosphere |
|
|
129 | (1) |
|
|
130 | (1) |
|
5.8.4 Change of Law or Taxation |
|
|
131 | (1) |
|
5.8.4.1 Contracting Agency Risk |
|
|
131 | (1) |
|
5.8.4.2 Apportionment of Cost |
|
|
131 | (1) |
|
5.8.4.3 Apportionment of Risk |
|
|
131 | (1) |
|
5.8.5 Change in Technical Requirements |
|
|
132 | (1) |
|
|
132 | (1) |
|
|
132 | (1) |
|
5.8.8 Political Risk Insurance |
|
|
133 | (1) |
|
5.8.9 Source Country Political Risks |
|
|
134 | (1) |
|
|
134 | (1) |
|
|
135 | (2) |
|
5.9.1 Lender Specific Issues |
|
|
135 | (1) |
|
5.9.2 Assessing Environmental Impact |
|
|
136 | (1) |
|
5.9.3 Managing Environmental Risk |
|
|
137 | (1) |
|
|
137 | (2) |
|
|
139 | (2) |
|
Chapter 6 Project Participant Interface Risk |
|
|
141 | (12) |
|
|
142 | (3) |
|
6.1.1 Technology Interfaces |
|
|
142 | (1) |
|
6.1.2 Methodology Interfaces |
|
|
142 | (3) |
|
6.1.2.1 Commercial Diversity |
|
|
142 | (1) |
|
6.1.2.2 Cultural Diversity |
|
|
143 | (2) |
|
6.1.3 Management and Allocation of Interface Risk |
|
|
145 | (1) |
|
6.2 Contracting Agency Interfaces |
|
|
145 | (3) |
|
6.2.1 Interfaces with Construction Contractor |
|
|
145 | (1) |
|
6.2.2 Interfaces with Operator |
|
|
146 | (1) |
|
6.2.3 Interfaces with Offtake Purchaser |
|
|
147 | (1) |
|
6.2.4 Interfaces with Input Supplier |
|
|
148 | (1) |
|
6.3 Construction Contractor and Operator |
|
|
148 | (3) |
|
6.4 Operator and Offtake Purchaser |
|
|
151 | (1) |
|
6.5 Operator and Input Supplier |
|
|
151 | (1) |
|
6.6 Intra-project Company Interfaces |
|
|
152 | (1) |
Part II Up-Stream: PPP Frameworks |
|
153 | (64) |
|
Chapter 7 Legal Framework |
|
|
155 | (10) |
|
7.1 Setting and Implementing the PPP Legal Policy |
|
|
155 | (3) |
|
7.2 Key Legal Constraints |
|
|
158 | (7) |
|
|
158 | (1) |
|
7.2.2 Government Obligations and Support |
|
|
158 | (1) |
|
7.2.3 Creation of Limited Liability Project Company |
|
|
158 | (1) |
|
|
158 | (1) |
|
7.2.5 Land Rights and Acquisition |
|
|
159 | (1) |
|
7.2.6 Setting and Collecting Tariffs |
|
|
159 | (1) |
|
7.2.7 Penalties, Sanctions and Bonuses |
|
|
159 | (1) |
|
7.2.8 Security Rights over Assets |
|
|
160 | (1) |
|
|
160 | (1) |
|
7.2.10 Sovereign Immunity |
|
|
160 | (1) |
|
|
161 | (1) |
|
|
161 | (1) |
|
7.2.13 Regulatory Frameworks |
|
|
161 | (1) |
|
7.2.14 Trusts, Agency and Other Legal Relationships |
|
|
162 | (1) |
|
|
162 | (3) |
|
Chapter 8 Institutional Framework |
|
|
165 | (12) |
|
8.1 Coordination of PPP Programme |
|
|
167 | (2) |
|
|
169 | (1) |
|
|
170 | (1) |
|
|
170 | (1) |
|
8.5 Demonstration Projects |
|
|
171 | (1) |
|
8.6 Preparation of Good Practice Contracts and Bid Documents |
|
|
172 | (1) |
|
|
173 | (1) |
|
|
174 | (3) |
|
Chapter 9 Procuring and Implementing Transactions |
|
|
177 | (14) |
|
9.1 Direct Negotiations and Unsolicited Proposals: or, Tendering Takes So Long and Is So Expensive...Why Bother? |
|
|
177 | (3) |
|
9.2 Inception/Pre-feasibility/Preliminary Viability Study/Outline Business Case |
|
|
180 | (1) |
|
9.3 Viability/Feasibility Study/Full Business Case |
|
|
181 | (2) |
|
|
183 | (1) |
|
|
184 | (1) |
|
|
185 | (1) |
|
|
185 | (1) |
|
9.8 Management/Monitoring of Implementation |
|
|
186 | (5) |
|
|
187 | (1) |
|
|
187 | (1) |
|
9.8.3 Monitoring Performance |
|
|
188 | (1) |
|
|
188 | (1) |
|
9.8.5 Selling Down Equity |
|
|
189 | (1) |
|
9.8.6 Dispute Resolution and Renegotiations |
|
|
189 | (1) |
|
9.8.7 Expiry, Termination and Handover |
|
|
190 | (1) |
|
Chapter 10 Using Public Financial Support for PPP |
|
|
191 | (12) |
|
10.1 The Fundamentals of Public Support |
|
|
192 | (2) |
|
10.2 Purposes for Public Support |
|
|
194 | (1) |
|
|
195 | (4) |
|
10.3.1 Grants/Capital Contributions |
|
|
195 | (2) |
|
10.3.2 Payments for Services Rendered |
|
|
197 | (1) |
|
|
198 | (1) |
|
|
198 | (1) |
|
|
199 | (2) |
|
10.4.1 Government Guarantees |
|
|
199 | (1) |
|
10.4.2 Contingent Debt/Equity |
|
|
200 | (1) |
|
10.4.3 Contingent Contributions |
|
|
200 | (1) |
|
10.4.4 Bilateral/Multilateral Guarantees |
|
|
201 | (1) |
|
10.5 Managing Government Liabilities |
|
|
201 | (2) |
|
10.5.1 Assessing Liabilities |
|
|
201 | (1) |
|
10.5.2 Monitoring/Accounting for Liabilities |
|
|
202 | (1) |
|
10.5.3 Paying for Liabilities Once They Crystallise |
|
|
202 | (1) |
|
Chapter 11 Mobilising Local Currency Financing |
|
|
203 | (14) |
|
11.1 Sources of Long-Term, Local Currency Funding |
|
|
204 | (3) |
|
11.2 Government Interventions That Can Facilitate Access to Long-Term Local Capital |
|
|
207 | (1) |
|
11.3 Using an Intermediary |
|
|
208 | (4) |
|
|
209 | (1) |
|
|
210 | (2) |
|
|
212 | (1) |
|
|
213 | (4) |
Part III Down-Stream: PPP Transactions |
|
217 | (230) |
|
Chapter 12 Concession Agreement |
|
|
219 | (18) |
|
|
222 | (2) |
|
|
222 | (1) |
|
|
223 | (1) |
|
|
223 | (1) |
|
12.1.4 Permits and Licences |
|
|
223 | (1) |
|
12.1.5 Transfer and Re-tendering |
|
|
224 | (1) |
|
|
224 | (2) |
|
12.2.1 Construction Contractor |
|
|
224 | (1) |
|
|
225 | (1) |
|
|
226 | (1) |
|
|
226 | (1) |
|
12.3 Payment and Guarantees |
|
|
226 | (3) |
|
|
226 | (1) |
|
|
226 | (1) |
|
12.3.3 Non-competition/Exclusivity |
|
|
227 | (1) |
|
12.3.4 Foreign Currency Exchange and Transfer of Funds |
|
|
227 | (1) |
|
|
227 | (1) |
|
12.3.6 Compensation Events |
|
|
228 | (1) |
|
12.3.7 Compensation on Termination |
|
|
228 | (1) |
|
12.4 Completion and Operation |
|
|
229 | (3) |
|
12.4.1 Design, Construction and Technical Requirements |
|
|
229 | (1) |
|
12.4.2 Modification of Technical Requirements |
|
|
229 | (1) |
|
12.4.3 Time for Completion and the Project Programme |
|
|
230 | (1) |
|
12.4.4 Method of Operation |
|
|
230 | (1) |
|
12.4.5 Maintenance Manuals, Records and As-Built Drawings |
|
|
231 | (1) |
|
12.4.6 Update of Project Technology |
|
|
231 | (1) |
|
|
231 | (1) |
|
12.4.8 No Discriminatory Action by Government Entity |
|
|
232 | (1) |
|
12.5 Procedures and Mechanisms |
|
|
232 | (5) |
|
12.5.1 Approval, Appointment and Replacement |
|
|
232 | (1) |
|
12.5.2 Granting the Concession |
|
|
233 | (1) |
|
|
233 | (1) |
|
12.5.4 Independent Expert |
|
|
233 | (1) |
|
12.5.5 Restrictions on Transfer of Shares of the Project Company |
|
|
233 | (1) |
|
12.5.6 Step-In and Continuous Operation Provisions |
|
|
234 | (1) |
|
12.5.7 Transfer or Re-tender |
|
|
234 | (3) |
|
Chapter 13 Shareholders' Agreement |
|
|
237 | (12) |
|
13.1 Development Agreement |
|
|
238 | (1) |
|
13.2 Form of the Project Company |
|
|
239 | (2) |
|
13.2.1 Added Source of Equity Capital |
|
|
239 | (1) |
|
13.2.2 Special Project Expertise |
|
|
239 | (1) |
|
13.2.3 Shareholder Interest |
|
|
239 | (1) |
|
13.2.4 Diversity of Ownership |
|
|
240 | (1) |
|
|
240 | (1) |
|
13.2.6 Off-Balance Sheet Treatment |
|
|
240 | (1) |
|
13.2.7 Availability of Funding |
|
|
241 | (1) |
|
13.2.8 Control over a Resource or Market Position |
|
|
241 | (1) |
|
13.3 Investment, Return, Costs and Cash Flow |
|
|
241 | (3) |
|
13.3.1 Shareholder Contributions |
|
|
241 | (2) |
|
|
242 | (1) |
|
13.3.1.2 Subordinated Debt |
|
|
242 | (1) |
|
13.3.1.3 Contributions in Kind |
|
|
242 | (1) |
|
13.3.2 New Equity Infusions |
|
|
243 | (1) |
|
13.3.3 Application of Cash Flow |
|
|
243 | (1) |
|
|
243 | (1) |
|
13.3.5 Contribution Clause |
|
|
244 | (1) |
|
13.4 Shareholder Rights and Obligations |
|
|
244 | (3) |
|
13.4.1 Shareholder Undertakings |
|
|
244 | (1) |
|
13.4.2 Conflicts of Interest |
|
|
244 | (1) |
|
|
245 | (1) |
|
13.4.4 Transfer to Contracting Agency |
|
|
246 | (1) |
|
13.4.5 Transfer of Shares |
|
|
246 | (1) |
|
13.5 Management and Administration |
|
|
247 | (2) |
|
|
247 | (1) |
|
13.5.2 Dispute Resolution |
|
|
247 | (2) |
|
Chapter 14 Construction Contract |
|
|
249 | (30) |
|
14.1 Turnkey Construction Contracts |
|
|
250 | (7) |
|
14.1.1 Single Point Responsibility |
|
|
251 | (3) |
|
|
251 | (1) |
|
|
252 | (1) |
|
|
252 | (1) |
|
14.1.1.4 Contractual Standard of Care |
|
|
253 | (1) |
|
14.1.1.5 Contractor's Claims |
|
|
254 | (1) |
|
14.1.2 Time for Completion |
|
|
254 | (1) |
|
|
255 | (1) |
|
|
256 | (1) |
|
14.1.4.1 Control of Design |
|
|
256 | (1) |
|
|
257 | (1) |
|
|
257 | (2) |
|
|
257 | (1) |
|
14.2.1.1 Concept of Completion |
|
|
257 | (1) |
|
14.2.1.2 Time for Completion |
|
|
258 | (1) |
|
|
258 | (1) |
|
14.3 Interfaces between Construction Contractor and Other Project Participants |
|
|
259 | (2) |
|
|
259 | (1) |
|
|
260 | (1) |
|
|
261 | (1) |
|
14.4 Completion and Performance |
|
|
261 | (5) |
|
|
261 | (1) |
|
|
262 | (1) |
|
|
263 | (1) |
|
|
263 | (1) |
|
14.4.5 Completion and Takeover |
|
|
264 | (1) |
|
14.4.6 Tests on Completion |
|
|
264 | (1) |
|
|
265 | (1) |
|
|
265 | (1) |
|
|
266 | (4) |
|
14.5.1 Time for Completion and Project Programme |
|
|
266 | (3) |
|
14.5.2 Defects Liability Period |
|
|
269 | (1) |
|
|
270 | (1) |
|
14.5.4 Equipment Supplier Maintenance |
|
|
270 | (1) |
|
|
270 | (4) |
|
|
270 | (1) |
|
|
271 | (2) |
|
14.6.3 Bonds, Guarantees and Retention |
|
|
273 | (1) |
|
14.6.4 Limitation of Liability |
|
|
274 | (1) |
|
14.6.5 Joint and Several Liability |
|
|
274 | (1) |
|
14.7 Additional Considerations |
|
|
274 | (5) |
|
14.7.1 Independent Engineer |
|
|
275 | (1) |
|
14.7.2 Training and Operation Manuals. |
|
|
275 | (1) |
|
14.7.3 Transfer of Title and Risk |
|
|
275 | (1) |
|
|
276 | (1) |
|
14.7.5 Procurement Restrictions |
|
|
276 | (1) |
|
14.7.6 Splitting Turnkey Contracts |
|
|
276 | (3) |
|
Chapter 15 Operation and Maintenance Agreement |
|
|
279 | (16) |
|
|
281 | (2) |
|
|
281 | (1) |
|
15.1.2 Increase of Cost Risk |
|
|
282 | (1) |
|
|
282 | (1) |
|
|
282 | (1) |
|
|
283 | (3) |
|
15.2.1 Construction Contractor |
|
|
284 | (1) |
|
|
285 | (1) |
|
|
285 | (1) |
|
15.2.4 Contracting Agency |
|
|
285 | (1) |
|
15.3 Operator's Obligations |
|
|
286 | (3) |
|
|
286 | (1) |
|
15.3.2 Standards of Performance |
|
|
287 | (1) |
|
|
287 | (1) |
|
15.3.4 Emergency Situations |
|
|
288 | (1) |
|
15.3.5 Procurement Restrictions |
|
|
288 | (1) |
|
|
288 | (1) |
|
15.3.7 Asset Removal/Replacement |
|
|
289 | (1) |
|
|
289 | (3) |
|
15.4.1 Cost of Operation and Payment |
|
|
289 | (2) |
|
15.4.2 Budgeting for Spare Parts, Major Maintenance and Asset Renewal |
|
|
291 | (1) |
|
|
291 | (1) |
|
|
291 | (1) |
|
15.4.5 Foreign Exchange and Convertibility |
|
|
291 | (1) |
|
15.5 Procedures for Performance and Compliance |
|
|
292 | (3) |
|
|
292 | (1) |
|
15.5.2 Independent Engineer |
|
|
292 | (1) |
|
15.5.3 Access to Books and Records |
|
|
292 | (1) |
|
15.5.4 Training of the Contracting Agency's Personnel |
|
|
293 | (1) |
|
|
294 | (1) |
|
Chapter 16 Offtake Purchase Agreement |
|
|
295 | (18) |
|
|
297 | (1) |
|
|
298 | (1) |
|
|
298 | (1) |
|
|
298 | (1) |
|
|
299 | (1) |
|
16.2.2 Construction Contractor |
|
|
299 | (1) |
|
|
299 | (3) |
|
|
300 | (1) |
|
|
300 | (1) |
|
16.3.3 Technical and Performance Specifications |
|
|
300 | (1) |
|
16.3.4 Modifications to the Project |
|
|
301 | (1) |
|
16.3.5 Facilities Provided by Offtake Purchaser |
|
|
301 | (1) |
|
16.3.6 Ancillary Services |
|
|
301 | (1) |
|
16.3.7 Completion and Transition |
|
|
302 | (1) |
|
16.3.8 Transfer to Contracting Agency |
|
|
302 | (1) |
|
|
302 | (7) |
|
|
304 | (1) |
|
|
305 | (1) |
|
|
305 | (1) |
|
|
306 | (1) |
|
16.4.5 Metering of Output |
|
|
306 | (1) |
|
|
307 | (1) |
|
16.4.7 Other Pricing Schemes |
|
|
307 | (1) |
|
|
308 | (1) |
|
|
308 | (1) |
|
16.4.10 Foreign Exchange Risk |
|
|
308 | (1) |
|
16.5 Mechanisms and Procedures |
|
|
309 | (4) |
|
|
309 | (1) |
|
16.5.2 Maintenance Regime |
|
|
309 | (1) |
|
|
310 | (3) |
|
Chapter 17 Input Supply Agreement |
|
|
313 | (14) |
|
|
315 | (1) |
|
|
315 | (1) |
|
|
316 | (1) |
|
|
316 | (1) |
|
|
316 | (1) |
|
17.2.2 Construction Contractor |
|
|
317 | (1) |
|
17.3 Principal Obligations |
|
|
317 | (5) |
|
|
317 | (1) |
|
17.3.2 Procurement Restrictions |
|
|
318 | (1) |
|
|
319 | (1) |
|
17.3.4 Shipment and Storage |
|
|
320 | (1) |
|
|
321 | (1) |
|
17.3.6 Completion and Transition |
|
|
321 | (1) |
|
|
322 | (3) |
|
|
322 | (1) |
|
17.4.2 Failure to Deliver |
|
|
323 | (1) |
|
|
324 | (1) |
|
17.4.4 Measuring Quantity |
|
|
324 | (1) |
|
|
324 | (1) |
|
|
325 | (1) |
|
17.5 Mechanisms and Procedures |
|
|
325 | (2) |
|
17.5.1 Independent Engineer |
|
|
325 | (1) |
|
17.5.2 Transfer to Contracting Agency |
|
|
325 | (2) |
|
Chapter 18 Issues Common to Project Documents |
|
|
327 | (34) |
|
|
327 | (3) |
|
18.1.1 Possession of and Access to the Site |
|
|
328 | (1) |
|
|
329 | (1) |
|
|
330 | (3) |
|
18.2.1 Procurement Restrictions |
|
|
330 | (1) |
|
18.2.2 Transfer of Title and Risk |
|
|
330 | (1) |
|
|
331 | (1) |
|
|
331 | (2) |
|
|
333 | (2) |
|
18.3.1 Price, Payment and Revenues |
|
|
333 | (1) |
|
18.3.2 Foreign Currency Exchange |
|
|
334 | (1) |
|
|
334 | (1) |
|
|
335 | (2) |
|
|
335 | (1) |
|
|
335 | (1) |
|
18.4.3 Change in Pricing Mechanism |
|
|
336 | (1) |
|
18.4.4 Change in Requirements |
|
|
336 | (1) |
|
|
336 | (1) |
|
18.4.6 Lenders' Interests |
|
|
337 | (1) |
|
18.5 Political and Natural Events |
|
|
337 | (10) |
|
18.5.1 Licences and Permits |
|
|
337 | (2) |
|
|
339 | (2) |
|
18.5.3 Sovereign Immunity |
|
|
341 | (1) |
|
18.5.4 Types of Insurance |
|
|
342 | (2) |
|
|
344 | (3) |
|
18.6 Termination and Step-In |
|
|
347 | (3) |
|
|
347 | (1) |
|
18.6.2 Step-in and Continuous Operation Provisions |
|
|
348 | (1) |
|
18.6.3 Transfer to Contracting Agency |
|
|
349 | (1) |
|
18.7 Supervision and Disputes |
|
|
350 | (3) |
|
18.7.1 Contracting Agency/Lender Access and Inspection |
|
|
350 | (1) |
|
18.7.2 Independent Engineer |
|
|
351 | (1) |
|
18.7.3 Dispute Resolution |
|
|
351 | (2) |
|
|
353 | (5) |
|
|
353 | (1) |
|
18.8.2 Conditions Precedent |
|
|
353 | (1) |
|
|
354 | (1) |
|
|
355 | (1) |
|
|
355 | (1) |
|
|
356 | (1) |
|
|
356 | (1) |
|
|
357 | (1) |
|
|
358 | (3) |
|
|
361 | (18) |
|
|
362 | (1) |
|
19.2 Associated Infrastructure |
|
|
362 | (1) |
|
|
363 | (1) |
|
|
364 | (1) |
|
|
364 | (1) |
|
19.6 Special Characteristics |
|
|
365 | (2) |
|
19.6.1 Greenhouse Gas Emissions |
|
|
365 | (1) |
|
|
366 | (1) |
|
|
366 | (1) |
|
19.6.4 Frequency Responsive Generation |
|
|
366 | (1) |
|
|
366 | (1) |
|
19.6.6 Peaking Power and Ramp Rate |
|
|
367 | (1) |
|
|
367 | (1) |
|
|
368 | (1) |
|
|
368 | (2) |
|
|
370 | (1) |
|
19.10.1 Commercial Specificities |
|
|
370 | (1) |
|
19.10.2 Environmental Specificities |
|
|
370 | (1) |
|
19.10.3 Environmental Impact |
|
|
371 | (1) |
|
|
371 | (3) |
|
19.11.1 Quantity of Waste |
|
|
372 | (1) |
|
|
372 | (1) |
|
19.11.3 Electricity Generation |
|
|
373 | (1) |
|
|
373 | (1) |
|
19.11.5 Landfill and Storage |
|
|
373 | (1) |
|
19.11.6 Emissions Requirements |
|
|
374 | (1) |
|
|
374 | (2) |
|
19.12.1 Competition and Cost |
|
|
376 | (1) |
|
|
376 | (3) |
|
19.13.1 Cost of Geothermal Development |
|
|
376 | (1) |
|
19.13.2 Combining Procurement of Steam with Electricity |
|
|
377 | (1) |
|
19.13.3 Encouraging Expansion by Existing Licence Holders |
|
|
378 | (1) |
|
Chapter 20 Transportation |
|
|
379 | (16) |
|
20.1 Roads, Bridges and Tunnels |
|
|
380 | (5) |
|
|
380 | (1) |
|
20.1.2 Revenues/Traffic Forecasts |
|
|
380 | (3) |
|
20.1.3 Permitting, Existing Facilities and Ground Conditions |
|
|
383 | (1) |
|
20.1.4 Land, Environmental and Social Risks |
|
|
384 | (1) |
|
|
385 | (4) |
|
|
385 | (1) |
|
20.2.2 Interface with Existing Facilities |
|
|
386 | (1) |
|
20.2.3 Land and the Environment |
|
|
386 | (1) |
|
20.2.4 Capital Cost and Subsidies |
|
|
387 | (1) |
|
|
387 | (1) |
|
20.2.6 Extension or Refurbishment of Existing Railways |
|
|
387 | (1) |
|
20.2.7 Regulation and Safety |
|
|
388 | (1) |
|
|
388 | (1) |
|
|
389 | (6) |
|
|
390 | (1) |
|
|
390 | (1) |
|
|
391 | (1) |
|
20.3.4 Design and Long-Term Planning |
|
|
392 | (1) |
|
20.3.5 Land and Environment |
|
|
393 | (1) |
|
|
393 | (2) |
|
Chapter 21 Telecommunications |
|
|
395 | (10) |
|
21.1 Telecommunications Projects |
|
|
395 | (2) |
|
|
396 | (1) |
|
|
396 | (1) |
|
|
397 | (1) |
|
21.2 Backbone Fibre-Optic Projects |
|
|
397 | (8) |
|
21.2.1 What is a Fibre Network? |
|
|
398 | (1) |
|
|
399 | (1) |
|
21.2.3 Construction Contracts |
|
|
400 | (1) |
|
|
401 | (1) |
|
|
402 | (1) |
|
|
403 | (2) |
|
Chapter 22 Water and Sanitation |
|
|
405 | (18) |
|
22.1 PPP and the Water Sector |
|
|
406 | (2) |
|
22.2 Key Characteristics of PPP Water Projects |
|
|
408 | (10) |
|
22.2.1 Offtake Purchase Agreement |
|
|
408 | (1) |
|
22.2.2 Rights of Water Abstraction |
|
|
409 | (1) |
|
|
410 | (1) |
|
22.2.4 Government Support |
|
|
410 | (1) |
|
|
411 | (1) |
|
22.2.6 Increasing Efficiency in the Water Sector |
|
|
411 | (2) |
|
22.2.7 Delivering Services to Low-Income Households |
|
|
413 | (1) |
|
|
414 | (1) |
|
|
415 | (1) |
|
22.2.10 Billing and Collection |
|
|
416 | (1) |
|
|
417 | (1) |
|
22.2.12 Metering and Measurement |
|
|
417 | (1) |
|
22.2.13 Point of Delivery |
|
|
418 | (1) |
|
22.3 Delivering Services to Consumers |
|
|
418 | (5) |
|
|
419 | (1) |
|
|
420 | (1) |
|
|
420 | (1) |
|
22.3.4 Tariff Levels and Payments |
|
|
421 | (2) |
|
Chapter 23 Sub-national/Small PPP |
|
|
423 | (12) |
|
|
424 | (2) |
|
|
424 | (1) |
|
|
425 | (1) |
|
|
425 | (1) |
|
23.1.4 Local Investment and Finance |
|
|
425 | (1) |
|
|
426 | (9) |
|
23.2.1 Small PPP Processes |
|
|
426 | (1) |
|
23.2.2 Centralised Support |
|
|
427 | (1) |
|
23.2.3 Standard Documents and Processes |
|
|
428 | (1) |
|
23.2.4 Pooling of Advisory Mandate |
|
|
429 | (1) |
|
23.2.5 Pooling of Projects into One |
|
|
430 | (1) |
|
|
431 | (1) |
|
23.2.7 Credit Enhancement |
|
|
431 | (1) |
|
|
431 | (1) |
|
23.2.9 Capacity and Experience |
|
|
432 | (3) |
|
Chapter 24 Commercial Facilities (and Tourism) |
|
|
435 | (12) |
|
24.1 Linkages to Public Assets and Support for Local Communities |
|
|
436 | (3) |
|
24.2 Competitive, Level Playing Field for Investors |
|
|
439 | (1) |
|
|
440 | (2) |
|
|
442 | (5) |
Glossary |
|
447 | (54) |
Index |
|
501 | |